1 Scope
This Part in DL/T 5210 specifies the relevant requirements in the construction quality acceptance standard for instrumentation and control device("instrumentation and control",or"I&C"),and quality evaluation for individual project,individual unit and overall project.
This Part is applicable to the construction quality acceptance and engineering quality evaluation of I&C device for newly-built,extended and rebuilt thermal power generation projects with unit capacity 300MW-1000MW.The unit capacity construction quality acceptance and evaluation of I&C device for thermal power generation project with unit capacity under 300MW may comply with this Part by reference.