6 Installation of Sintering Equipment

6.1 General Requirement

6.1.1 This chapter applies to belt-type sinter machine,include framework,feeding divice,driving device,portfire device,rail,sealing slide and sealing plate,translation pulley,fixed bending rail,trolley,heat crusher,main exhaust tube,ash bucket and chute.

6.1.2 The longitudinal centerline shall be set before installation of the sinter machine,and center plotting plate should be set both at the head and tail of the machine to decide the longitudinal center line for installation.More temporary center plotting plates may be set for survey if the product line of sinter machine is too long.

6.1.3 The transversal centerline shall be set before installation of sinter machine,which shall be perpendicular to longitudinal centerline of the machine,which shall include:axial centerline of head wheel of machine,transversal centerline of framework at the middle of machine,axial centerline of tail wheel of machine,axial centerline of ratch roll of heat crusher.

6.1.4 The bench mark shall be set before installation of sinter machine,which shall be set at the front part,middle part and rear part of the sinter machine.