According to the requirements of Jian Biao Han[2006]No.136 issued by former Ministry of Construction"Notice on Printing the Development and Revision Plan of National Engineering Construction Standards in 2006(second batch)",this code is hereby established by China First Metallurgical Group Co.,Ltd.jointly with related companies.

During establishment of the code,the preparation group has made extensive and in-depth investigation;concluded many years'experience in the installation of steel-making mechanical equipment engineering;widely sought the advice and suggestions from related companies and experts;repeatedly discussed,revised and enhanced the provisions of the code and finalized this text upon review.

The code consists of nineteen chapters with the main contents as follows:General provisions,basic requirements,equipment foundation,foundation bolt and base plate,equipment and material mobilization,converter installation,installation of oxygen lance and sublance,installation of hood,installation of waste heat boiler,installation of electric arc furnace,installation of ladle refining furnace,installation of vacuum ladle refining furnace and vacuum oxygen decarburization converter,installation of recirculation vacuum degassing refining furnace,installation of casting equipment,installation of continuous steel-casting equipment,installation of discharging and finishing equipment,installation of hot metal mixer,installation of hot metal pretreatment equipment,test run of mechanical steel-making,safety and environmental protection,etc.

The provisions printed in bold type in this code are mandatory,and shall be enforced strictly.Ministry of housing and urban-rural development is in charge of the management of the code and the explanation of the mandatory provisions,China metallurgical construction association is in charge of daily management,while China first metallurgical group Co.,Ltd.is responsible for explanation of the specific technical contents.All relevant companies are kindly requested to sum up and accumulate experiences in actual practices during the process of implementing this code.The relevant opinions and advice,whenever necessary,can be posted or passed on to China First Metallurgical Group Co.,Ltd.(address:No.3 Gongye Avenue,Qingshan District,Wuhan city,Hubei province;Zip code:430081;E-mail:jisc@ccfmcc.com or xiaolw@cfmcc.com;Fax:027-86308221)for reference in case of future revision of this code.

Chief Development Organization,Participating Development Organizations as well as Chief Drafting Staff and Main Reviewers of the code are as follows:

Chief Development Organization:

      China First Metallurgical Group Co.,Ltd.

Participating Development Organizations:

      MCC TianGong Group Corporation Limited

      China MCC20 Group Corp.,Ltd.

Chief Drafting Staff:

      Zou Yichang Ai Qingzhu Liu Yiming Xiao Liwen Zhang Li

      Luo Jin Cai Xiaobo Li Shaoxiang Zheng Guoqiang Jing Dewei

      Min Li

Main Reviewers:

      Yu Huachun Guo Qijiao Zhang Yongxin Li Xin Yan Yu

      Zheng Yongheng Wu Mingfu Li Changliang Lu Fuli Zhao Cong

      Sun Qing