6.3 Cross travelling device
General Items
6.3.1 The allowable deviation for installation of single-rail cross travelling device shall comply with the requirements in Table 6.3.1(see Figure 6.3.1).
Quantity to be checked:100%.
Inspection method:See Table 6.3.1.
Table 6.3.1 Allowable deviation for installation of single-rail cross travelling device
![img](https://epubservercos.yuewen.com/5DC1A6/18000635001102306/epubprivate/OEBPS/Images/txt006_3.jpg?sign=1738999044-dcDIdYN9D5tg77HmPXn5ZlswxVTFn5YL-0-8027850f4f07be79eb52f4a36c4d933b)
![img](https://epubservercos.yuewen.com/5DC1A6/18000635001102306/epubprivate/OEBPS/Images/txt006_4.jpg?sign=1738999044-SpGI4Rq79NGvqRgKa6zFs2eUDiAiza9q-0-b9aba2a7461f5375dd6cfa7d1b7e12e0)
Figure 6.3.1 Schematic drawing for installation of single-rail track and guide rail for cross travelling trolley
1-lower guide rail;2-upper guide rail;3-track
6.3.2 The allowable deviation for installation of double-rail cross travelling device shall comply with the requirements in Table 6.3.2.
Quantity to be checked:100%.
Inspection method:See Table 6.3.2.
Table 6.3.2 Allowable deviation for installation of double-rail cross travelling device
![img](https://epubservercos.yuewen.com/5DC1A6/18000635001102306/epubprivate/OEBPS/Images/txt006_5.jpg?sign=1738999044-CcidPShz91ouwm0AsXK4Pk3jL0WNoUkz-0-fc4c5b2ef481f362c7799fa0c933db55)